Government

Public Works
Administration

6300 Southcenter Blvd.,
Tukwila, WA 98188

Phone: 206 433-0179
Fax: 206 431-3665

Email the Public Works Dept.

Annual Overlay and Repair Program

The Overlay and Repair Program preserves and maintains the street structure in a safe and usable condition. Construction will include, but not be limited to pavement repairs, sidewalk improvements, signal improvements, and an asphalt overlay at seven locations citywide. This year, we added additional work such as small drainage, ADA improvements, Traffic Calming, and signal improvements.

This contract was awarded to Tucci & Sons as the lowest responsible bidder. We are working on executing this contract and beginning work by the middle of July. KPG is contracted out to provided construction management duties for this project. See below for the specific locations that will be worked on this summer/fall.

 

Project Status Update

 

Orillia Road & S. 200th St.

Tucci & Sons has been contracted by the City of Tukwila, to perform pavement restoration and signal improvements along Orillia Road in the area highlighted on the attached map.  During construction, traffic will be impacted by roadway grinding and paving as well as select improvements to the pedestrian crosswalks.  While some of this work will be performed during normal business hours, the grinding and paving will occur at night.

Minor lane restrictions should be in place during daytime operations.  Lane closures and detours will be required for grinding and paving.  Because the most disruptive activities will be outside of normal business hours, we expect only minor impact to traffic during this work.

DATES:
August – September 2022

HOURS OF CONSTRUCTION:
Typical daytime work hours: 07:00 AM – 06:00PM

Grinding &Paving Hours: 08:00 PM – 06:00 AM

 

S. 144th St. & 46th Ave. S

During construction, traffic will be impacted by partial pavement removal, utility placement, and crosswalk adjustments. Various construction activities will require lane restrictions and alternating one way traffic.  Delays through the work zone should be anticipated.

DATES:
August – September 2022

HOURS OF CONSTRUCTION:
Typical daytime work hours: 07:00 AM – 06:00PM

 

37th Ave S between S 144th St. And S 140th St

During construction, traffic will be impacted by partial pavement removal, utility placement, repaving and lane striping activities.  Traffic will be restricted to local access only in this area during some construction activities.  Access will be completely restricted during grinding and paving.  Construction notices will be provided by the contractor prior to any road closures.

DATES:
August – October 2022

HOURS OF CONSTRUCTION:
Typical daytime work hours: 07:00 AM – 06:00PM

 

44th Ave S and 46th Ave S along S 124th St

During construction, traffic will be impacted by partial pavement removal, ADA sidewalk improvements, minor utility work, and crosswalk adjustments. Various construction activities will require lane restrictions and alternating one way traffic.  Delays through the work zone should be anticipated.

DATES:
August – October 2022

HOURS OF CONSTRUCTION:
Typical daytime work hours: 07:00 AM – 06:00PM

 

 

Future Projects

  • S 140th St. From Military Road to TIB (Tukwila International Boulevard): Work includes grind and overlay, sidewalk and curb ramps installation, channelization such as stop bars, crosswalk and paint lines, speed cushions, signs, driveway improvements, pavement repair, and gravel.
  • S 141st St. From 37th to Tukwila International Blvd.: Work includes grind and overlay, pavement repair, installing gravel, driveway improvements, and channelization installation.
  • S 142nd St. From 37th to Tukwila International Blvd.: Work includes grind and overlay, pavement repair, installing gravel, driveway improvements, and channelization installation.
  • 37th Ave S between S 144th St. And S 140th St.: This section includes the small drainage work of adding new storm drainpipe by saw cutting out the pavement, then restoring that pavement with new pavement. Other work includes grind and overlay, gravel, HMA thickened edge, driveway improvements, speed cushions, and channelization.

 

Signup for the Project Mailing List

 

 

PROJECT CONTACTS:

City of Tukwila: Mike Ronda, Project Manager – 206-433-7194

Tucci & Sons: Troy Ilhen, Project Manager/ Superintendent – 253-349-1144

Tucci & Sons: Tony Alia, Foreman – 253-606-9677

KPG: Matt North, Resident Engineer – 206-310-7544